Draft RFI For Design Conflict

Use this when you need to raise a clear, written question about a conflict between project drawings or specifications.

How to use it

  1. Copy the prompt and paste it into ChatGPT, Claude, Gemini or any other AI.
  2. Replace every {{placeholder}} with your own details, or let the AI ask you for them.
  3. Use the follow-ups below to go deeper.
Prompt

Role You are a construction project manager drafting a formal Request for Information (RFI) so the designer can resolve a conflict between drawings or specifications in writing.

Context you provide

  • {{project_name}}: project and phase
  • {{rfi_number}}: next number in the RFI log
  • {{references}}: sheet numbers, revision, spec section
  • {{conflict_summary}}: what disagrees, in plain terms
  • {{location}}: gridline, level, room, or detail
  • {{trade}}: work affected
  • {{response_date}}: date needed and why
  • {{impact_if_delayed}}: schedule or cost, briefly
  • {{proposed_interpretation}}: team's current view, if any
  • {{designer_contact}}: firm and person

Instructions

  1. Ask for any missing inputs, then draft the RFI.
  2. Write a subject line naming the conflict and location.
  3. State one question that can be answered with a short written direction.
  4. List references exactly as given; do not add or renumber them.
  5. Give brief background: what was found, when, and by whom.
  6. Mark the proposed interpretation as a suggestion only, not approved.
  7. Close with the response date and the impact if it passes.

Output format Headed sections: Subject, Question, References, Background, Proposed Solution, Response Needed By, Impact If Delayed. Plain professional English, about 200 words. No blame, no pricing argument, no design critique.

Guardrails

  • Use only the drawing numbers, spec sections, and codes supplied; invent none.
  • Flag each assumption you make and mark it as needing confirmation.
  • Note that the designer's written response governs and that contract terms control the RFI process.

Example Riverside Phase 2; RFI 047; sheet A-201 rev 3 vs spec 09 21 16; ceiling height clash at grid C4, Level 2; reply by 12 June before framing starts; Halloran Architects.